CONTOH ANALISA PEKERJAAN BONGKARAN
X | PEKERJAAN BONGKARAN : | |||||||||
1 | Bongkar dinding 1/2 batu | M2 | pekerja | 0.2 | org/hr | |||||
mandor | 0.01 | org/hr | ||||||||
2 | Bongkar dinding 1/2 batu | M3 | pekerja | 2 | org/hr | |||||
mandor | 0.1 | org/hr | ||||||||
3 | Bongkar batu kali | M3 | pekerja | 1.5 | org/hr | |||||
(tebal < 50 cm) | mandor | 0.075 | org/hr | |||||||
4 | Bongkar batu kali | M3 | pekerja | 3 | org/hr | |||||
(tebal < 50 cm) | mandor | 0.15 | org/hr | |||||||
5 | Bongkar beton | M3 | tukang | 1.2 | org/hr | |||||
kepala tukang | 0.12 | org/hr | ||||||||
pekerja | 6 | org/hr | ||||||||
mandor | 0.3 | org/hr | ||||||||
6 | Bongkar beton bertulang | M3 | tukang | 1.6 | org/hr | |||||
kepala tukang | 0.16 | org/hr | ||||||||
pekerja | 8 | org/hr | ||||||||
mandor | 0.4 | org/hr | ||||||||
7 | Bongkar lantai | M2 | pekerja | 0.1 | org/hr | |||||
mandor | 0.01 | org/hr | ||||||||
8 | Bongkar plesteran | M2 | pekerja | 0.05 | org/hr | |||||
mandor | 0.0025 | org/hr | ||||||||
9 | Bongkar atas genteng | M2 | pekerja | 0.02 | org/hr | |||||
mandor | 0.01 | org/hr | ||||||||
10 | Bongkar karpusan atap genteng | M2 | pekerja | 0.03 | org/hr | |||||
mandor | 0.015 | org/hr | ||||||||
11 | Bongkar atap seng/asbes | M2 | tk. Besi | 0.05 | org/hr | |||||
pekerja | 0.01 | org/hr | ||||||||
12 | Bongkar kaso & reng kayu | M2 | tk. Kayu | 0.025 | org/hr | |||||
(kayu tidak dipakai lagi) | ke. Tk. Kayu | 0.0025 | org/hr | |||||||
pekerja | 0.1 | org/hr | ||||||||
mandor | 0.005 | org/hr | ||||||||
13 | Bongkar rangka atap kuda-2 kayu | M3 | tukang kayu | 1 | org/hr | |||||
kepala tukang | 0.2 | org/hr | ||||||||
14 | Bongkar plafond + rangka | M2 | pekerja | 0.04 | org/hr | |||||
mandor | 0.02 | org/hr | ||||||||
15 | Bongkar lisplank | M' | pekerja | 0.03 | org/hr | |||||
mandor | 0.015 | org/hr | ||||||||
16 | Bongkar kusen pintu | M3 | tukang | 1 | org/hr | |||||
kepala tukang | 0.1 | org/hr | ||||||||
17 | Bongkar daun pintu | M2 | pekerja | 0.02 | org/hr | |||||
mandor | 0.001 | org/hr | ||||||||
18 | Bongkar kaca | M2 | pekerja | 0.03 | org/hr | |||||
mandor | 0.003 | org/hr | ||||||||
19 | Bongkar rabat beton | M2 | pekerja | 0.05 | org/hr | |||||
mandor | 0.0025 | org/hr | ||||||||
20 | Bongkar bak air teraso | BH | pekerja | 0.3 | org/hr | |||||
mandor | 0.015 | org/hr |