II. | PEKERJAAN TANAH : | | | | | | | | | |
| | | | | | | | | | |
12 | Stripping tanah tebal 20 cm | | | | m2 | pekerja | | | 0.05 | org/hr |
| | | | | | mandor | | | 0.005 | org/hr |
| | | | | | | | | | |
13 | Galian tanah, dalam s/d 1 m | | | | m3 | pekerja | | | 0.6 | org/hr |
| | | | | | mandor | | | 0.02 | org/hr |
| | | | | | | | | | |
14 | Galian tanah, dalam s/d 2 m | | | | M3 | pekerja | | | 0.75 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
15 | Galian tanah, dalam s/d 3 m | | | | M3 | pekerja | | | 1.05 | org/hr |
| | | | | | mandor | | | 0.04 | org/hr |
| | | | | | | | | | |
16 | Galian tanah, dalam s/d 4 m | | | | M3 | pekerja | | | 1.35 | org/hr |
| | | | | | mandor | | | 0.05 | org/hr |
| | | | | | | | | | |
17 | Galian tanah keras s/d 1 m | | | | M3 | pekerja | | | 0.9 | org/hr |
| | | | | | mandor | | | 0.033 | org/hr |
| | | | | | | | | | |
18 | Galian tanah banyak batu s/d 1 m | | | | M3 | pekerja | | | 1.5 | org/hr |
| | | | | | mandor | | | 0.05 | org/hr |
| | | | | | | | | | |
19 | Galian tanah lumpur s/d 1 m | | | | M3 | pekerja | | | 0.75 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
20 | Galian tanah sumuran | | | | M3 | pekerja | | | 1.5 | org/hr |
| max dalam 10 | | | | | mandor | | | 0.05 | org/hr |
| | | | | | | | | | |
21 | Galian tanah cadas s/d 1 m | | | | M3 | pekerja | | | 1.75 | org/hr |
| | | | | | mandor | | | 0.375 | org/hr |
| | | | | | | | | | |
22 | Angkat tanah lumpur dari galian | | | | M3 | pekerja | | | 0.75 | org/hr |
| dalam galian s/d 3 m | | | | | mandor | | | 0.375 | org/hr |
| | | | | | | | | | |
23 | Urugan tanah kembali | | | | M3 | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
24 | Urugan tanah kembali dipadatkan | | | | M3 | pekerja | | | 0.6 | org/hr |
| | | | | | mandor | | | 0.05 | org/hr |
| | | | | | sewa stamper | | | 1 | unit |
| | | | | | | | | | |
25 | Pemadatan tanah tiap 20 cm | | | | M3 | tanah merah | | | 1.2 | m3 |
| (tanah didatangkan) | | | | | sewa stamper | | | 1 | unit |
| | | | | | pekerja | | | 0.4 | org/hr |
| | | | | | mandor | | | 0.04 | org/hr |
| | | | | | ongkos angkut truk +/- 20 km | | | 1.2 | m3 |
| | | | | | | | | | |
26 | Pemadatan tanah tiap 20 cm | | | | M3 | sewa stamper | | | 1 | unit |
| | | | | | pekerja | | | 0.4 | org/hr |
| | | | | | mandor | | | 0.04 | org/hr |
| | | | | | | | | | |
27 | Urugan pasir urug | | | | M3 | pasir urug | | | 1.2 | m3 |
| | | | | | pekerja | | | 0.25 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
28 | Urugan sirtu + pemandatan | | | | M3 | sirtu | | | 1.2 | m3 |
| | | | | | pekerja | | | 0.3 | org/hr |
| | | | | | mandor | | | 0.02 | org/hr |
| | | | | | pemadatan | | | 1 | m3 |
| | | | | | | | | | |
29 | Urugan sirtu 20 cm, dipadatkan | | | | M2 | sirtu | | | 0.24 | m3 |
| | | | | | pekerja | | | 0.06 | org/hr |
| | | | | | mandor | | | 0.004 | org/hr |
| | | | | | pemadatan | | | 0.2 | m3 |
| | | | | | | | | | |
30 | Urugan sirtu 25 cm, dipadatkan | | | | M2 | sirtu | | | 0.3 | m3 |
| | | | | | pekerja | | | 0.075 | org/hr |
| | | | | | mandor | | | 0.005 | org/hr |
| | | | | | pemadatan | | | 0.25 | m3 |
| | | | | | | | | | |
31 | Urugan sirtu 30 cm, dipadarkan | | | | M2 | sirtu | | | 0.36 | m3 |
| | | | | | pekerja | | | 0.09 | org/hr |
| | | | | | mandor | | | 0.006 | org/hr |
| | | | | | pemadatan | | | 0.3 | m3 |
| | | | | | | | | | |
32 | Angkut tanag sejauh s/d 30 m | | | | M2 | pekerja | | | 0.33 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
33 | Angkut tanah sejauh s/d 100 m | | | | M3 | pekerja | | | 0.6 | org/hr |
| | | | | | mandor | | | 0.02 | org/hr |
| | | | | | | | | | |
34 | Angkut tanah sejauh s/d 500 m | | | | M3 | pekerja | | | 0.6 | org/hr |
| dengan gerobak | | | | | mandor | | | 0.015 | org/hr |
| | | | | | | | | | |
35 | Pek angkutan truk (kap.m3) | | | | M3 | upah | | | 1 | m3 |
| jarak +/- 20 km | | | | | | | | | |
| | | | | | | | | | |
36 | Pek. Angkutan truk kecil (kap.4 m3) | | | | M3 | upah | | | 4 | m3 |
| jarak +/- 20 m) | | | | | | | | | |
| | | | | | | | | | |
37 | Pek. Angkutan truk kecil (kap.6 m3) | | | | M3 | upah | | | 1 | m3 |
| jarak +/- 20 m) | | | | | | | | | |
| | | | | | | | | | |
38 | Pek. Angkutan truk besar (kap.6 m3) | | | | RIT | upah | | | 6 | m3 |
| jarak +/- 20 m) | | | | | | | | | |
| | | | | | | | | | |
39 | Pek. Angkutan truk kap.4 m3 | | | | M3 | upah | | | 1 | m3 |
| jarak dekat (s/d 20 km) | | | | | | | | | |
| | | | | | | | | | |
40 | Pek. Angkutan truk kap. 6 m3 | | | | M3 | upah | | | 1 | m3 |
| jarak dekat (s/d 20 km) | | | | | | | | | |
| | | | | | | | | | |
41 | Pek. Cut & Fill | | | | M3 | Stripping | | | 1 | m3 |
| (Tenaga orang) | | | | | Galian tanah s/d 1m | | | 1 | m3 |
| | | | | | Angkut tanah kembali (padat) | | | 1 | m3 |