VII | PEKERJAAN WATER PROOFING | | | | | | | | | |
| | | | | | | | | | |
1 | Screeding tebal 3 cm | | | | M2 | semen | | | 0.288 | zak |
| | | | | | pasir beton | | | 0.039 | m3 |
| | | | | | tukang batu | | | 0.1 | org/hr |
| | | | | | kepala tukang batu | | | 0.01 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
2 | Screeding tebal 2 cm | | | | M2 | semen | | | 0.2 | zak |
| | | | | | pasir beton | | | 0.026 | m3 |
| | | | | | tukang batu | | | 0.1 | org/hr |
| | | | | | kepala tukang batu | | | 0.01 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
3 | Pekerjaan water proofing (coating) | | | | M2 | pre treatment/ cleaning | | | 1 | m2 |
| | | | | | curbing sudut | | | 0.4 | m' |
| | | | | | bahan waterproofting coating | | | 2.5 | kg |
| | | | | | sewa mixer | | | 0.02 | bh |
| | | | | | kuas | | | 0.2 | unit |
| | | | | | tukang batu | | | 0.2 | org/hr |
| | | | | | kepala tukang batu | | | 0.02 | org/hr |
| | | | | | pekerja | | | 0.1 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
4 | Pekerjaan water proofing (membrance) | | | | M2 | material primer | | | 0.3 | kg |
| | | | | | water proofing membrnce | | | 1.05 | m2 |
| | | | | | tukang batu | | | 0.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.25 | org/hr |
| | | | | | mandor | | | 0.0125 | org/hr |
| | | | | | | | | | |
5 | Pekerjaan Floor Hardener | | | | M2 | Material natural non metalic | | | 6 | kg |
| | | | | | Curing compound | | | 0.125 | ltr |
| | | | | | tukang batu | | | 0.15 | org/hr |
| | | | | | kepala tukang batu | | | 0.015 | org/hr |
| | | | | | pekerja | | | 0.075 | org/hr |
| | | | | | mandor | | | 0.0075 | org/hr |