Analisa Pekerjaan Waterproofing

VIIPEKERJAAN WATER PROOFING
1Screeding tebal 3 cmM2semen0.288zak
pasir beton0.039m3
tukang batu0.1org/hr
kepala tukang batu0.01org/hr
pekerja0.2org/hr
mandor0.01org/hr
2Screeding tebal 2 cmM2semen0.2zak
pasir beton0.026m3
tukang batu0.1org/hr
kepala tukang batu0.01org/hr
pekerja0.2org/hr
mandor0.01org/hr
3Pekerjaan water proofing (coating)M2pre treatment/ cleaning1m2
curbing sudut0.4m'
bahan waterproofting coating2.5kg
sewa mixer0.02bh
kuas0.2unit
tukang batu0.2org/hr
kepala tukang batu0.02org/hr
pekerja0.1org/hr
mandor0.01org/hr
4Pekerjaan water proofing (membrance)M2material primer0.3kg
water proofing membrnce1.05m2
tukang batu0.5org/hr
kepala tukang batu0.05org/hr
pekerja0.25org/hr
mandor0.0125org/hr
5Pekerjaan Floor HardenerM2Material natural non metalic6kg
Curing compound0.125ltr
tukang batu0.15org/hr
kepala tukang batu0.015org/hr
pekerja0.075org/hr
mandor0.0075org/hr