Analisa Pekerjaan Plesteran

VPEKERJAAN PLESTERAN
1Plesteran dinding 1:2 + acianM2semen0.24zak
tebal 15 mmpasir pasang0.02m3
tk. Batu0.214org/hr
kepala tukang batu0.021org/hr
pekerja0.4org/hr
mandor0.02org/hr
2Plesteran dinding 1:3 + acianM2semen0.1632zak
tebal 15 mmpasir pasang0.0194m3
tk. Batu0.214org/hr
kepala tukang batu0.021org/hr
pekerja0.4org/hr
mandor0.02org/hr
3Plesteran dinding 1:4 + acianM2semen0.1302zak
tebal 15 mmpasir pasang0.021m3
tk. Batu0.214org/hr
kepala tukang batu0.021org/hr
pekerja0.4org/hr
mandor0.02org/hr
4Acian PCM2semen0.08zak
tk. Batu0.11org/hr
kepala tukang batu0.011org/hr
pekerja0.14org/hr
mandor0.01org/hr
5Brapen pondasi 1:4M2semen0.085zak
pasir pasang0.17m3
tk. Batu0.09org/hr
kepala tukang batu0.009org/hr
pekerja0.18org/hr
mandor0.009org/hr