Analisa Pekerjaan Pasangan

IVPEKERJAAN PASANGAN
1Aanstamping batu kaliM3batu kali1.2m3
pasir pasang0.44m3
pekerja1.5org/hr
mandor0.075org/hr
2Pas. Pondasi batu kali 1:2M3batu kali1.2m3
semen3.52zak
pasir pasang0.38m3
tk. Batu0.6org/hr
kepala tukang batu0.06org/hr
pekerja2.25org/hr
mandor0.017org/hr
3Pas. Pondasi batu kali 1:4M3batu kali1.2m3
semen1.76zak
pasir pasang0.76m3
tk. Batu0.6org/hr
kepala tukang batu0.06org/hr
pekerja2.25org/hr
mandor0.017org/hr
4Pas. Pondasi batu kali 1:4M3batu kali1.5m3
memakai batu muka + siaransemen1.76zak
pasir pasang0.76m3
tk. Batu1.2org/hr
kepala tukang batu0.12org/hr
pekerja2.25org/hr
mandor0.017org/hr
5Pas. Batu tempel + siaranM3batu tempel1.1m2
semen0.12zak
pasir pasang0.032m3
tk. Batu0.3org/hr
kepala tukang batu0.05org/hr
pekerja0.375org/hr
mandor0.034org/hr
6Pas. Pondasi rollag bata 1:4M3batu bata merah475bh
semen2.4zak
pasir pasang0.416m3
tk. Batu1.5org/hr
kepala tukang batu0.15org/hr
pekerja3org/hr
mandor0.15org/hr
7Pas. Pondasi roollag bata 1:4M'0.07
8Pas. Dinding batu bata 1:2M2batu bata merah75bh
semen0.58zak
pasir pasang0.047m3
tk. Batu0.2org/hr
kepala tukang batu0.02org/hr
pekerja0.5org/hr
mandor0.025org/hr
9Pas. Dinding batu bata 1:4M2batu bata merah75bh
semen0.354zak
pasir pasang0.057m3
tk. Batu0.2org/hr
kepala tukang batu0.02org/hr
pekerja0.5org/hr
mandor0.025org/hr
10Pas. Dinding batu bata 1:2M3batu bata merah500bh
semen4.12zak
pasir pasang0.333m3
tk. Batu1.5org/hr
kepala tukang batu0.15org/hr
pekerja4.5org/hr
mandor0.225org/hr
11Pas. Dinding batu bata 1:4M3batu bata merah500bh
semen2.53zak
pasir pasang0.406m3
tk. Batu1.5org/hr
kepala tukang batu0.15org/hr
pekerja4.5org/hr
mandor0.225org/hr
12Pas. Rooster beton 20x20x7M2rooster beton 20.20.7 cm25bh
adukan 1:2semen0.172zak
pasir pasang0.017m3
tk. Batu0.18org/hr
kepala tukang batu0.018org/hr
pekerja0.54org/hr
mandor0.027org/hr
13Pas. Rooster bata merahM2rooster bata merah33bh
uk. 12x12x11.5semen0.2zak
adukan 1:2pasir pasang0.016m3
tk. Batu0.18org/hr
kepala tukang batu0.018org/hr
pekerja0.54org/hr
mandor0.027org/hr
14Pas. Bataco press 40x19x9M2bataco press13bh
adukan 1:2semen0.103zak
pasir pasang0.02m3
tk. Batu0.18org/hr
kepala tukang batu0.018org/hr
pekerja0.54org/hr
mandor0.027org/hr

4 Responses to "Analisa Pekerjaan Pasangan"

  1. Yg nomor 7 kak, butuh brp buah bata dan sak semen untuk 1 meter pondasi bata rollag, tnks admim

    ReplyDelete
  2. Halo, saya mau tanya analisa diatas itu dari pendekatan perhitungan lapangan atau ada dasarny sendiri serti dari analisa?

    ReplyDelete

partukang.com tidak bertanggung jawab atas isi komentar yang ditulis. Komentar sepenuhnya menjadi tanggung jawab komentator seperti diatur dalam UU ITE