X | PEKERJAAN BONGKARAN : | | | | | | | | | |
| | | | | | | | | | |
1 | Bongkar dinding 1/2 batu | | | | M2 | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
2 | Bongkar dinding 1/2 batu | | | | M3 | pekerja | | | 2 | org/hr |
| | | | | | mandor | | | 0.1 | org/hr |
| | | | | | | | | | |
3 | Bongkar batu kali | | | | M3 | pekerja | | | 1.5 | org/hr |
| (tebal < 50 cm) | | | | | mandor | | | 0.075 | org/hr |
| | | | | | | | | | |
4 | Bongkar batu kali | | | | M3 | pekerja | | | 3 | org/hr |
| (tebal < 50 cm) | | | | | mandor | | | 0.15 | org/hr |
| | | | | | | | | | |
5 | Bongkar beton | | | | M3 | tukang | | | 1.2 | org/hr |
| | | | | | kepala tukang | | | 0.12 | org/hr |
| | | | | | pekerja | | | 6 | org/hr |
| | | | | | mandor | | | 0.3 | org/hr |
| | | | | | | | | | |
6 | Bongkar beton bertulang | | | | M3 | tukang | | | 1.6 | org/hr |
| | | | | | kepala tukang | | | 0.16 | org/hr |
| | | | | | pekerja | | | 8 | org/hr |
| | | | | | mandor | | | 0.4 | org/hr |
| | | | | | | | | | |
7 | Bongkar lantai | | | | M2 | pekerja | | | 0.1 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
8 | Bongkar plesteran | | | | M2 | pekerja | | | 0.05 | org/hr |
| | | | | | mandor | | | 0.0025 | org/hr |
| | | | | | | | | | |
9 | Bongkar atas genteng | | | | M2 | pekerja | | | 0.02 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
10 | Bongkar karpusan atap genteng | | | | M2 | pekerja | | | 0.03 | org/hr |
| | | | | | mandor | | | 0.015 | org/hr |
| | | | | | | | | | |
11 | Bongkar atap seng/asbes | | | | M2 | tk. Besi | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.01 | org/hr |
| | | | | | | | | | |
12 | Bongkar kaso & reng kayu | | | | M2 | tk. Kayu | | | 0.025 | org/hr |
| (kayu tidak dipakai lagi) | | | | | ke. Tk. Kayu | | | 0.0025 | org/hr |
| | | | | | pekerja | | | 0.1 | org/hr |
| | | | | | mandor | | | 0.005 | org/hr |
| | | | | | | | | | |
13 | Bongkar rangka atap kuda-2 kayu | | | | M3 | tukang kayu | | | 1 | org/hr |
| | | | | | kepala tukang | | | 0.2 | org/hr |
| | | | | | | | | | |
14 | Bongkar plafond + rangka | | | | M2 | pekerja | | | 0.04 | org/hr |
| | | | | | mandor | | | 0.02 | org/hr |
| | | | | | | | | | |
15 | Bongkar lisplank | | | | M' | pekerja | | | 0.03 | org/hr |
| | | | | | | | | | |
| | | | | | mandor | | | 0.015 | org/hr |
16 | Bongkar kusen pintu | | | | M3 | tukang | | | 1 | org/hr |
| | | | | | kepala tukang | | | 0.1 | org/hr |
| | | | | | | | | | |
17 | Bongkar daun pintu | | | | M2 | pekerja | | | 0.02 | org/hr |
| | | | | | mandor | | | 0.001 | org/hr |
| | | | | | | | | | |
18 | Bongkar kaca | | | | M2 | pekerja | | | 0.03 | org/hr |
| | | | | | mandor | | | 0.003 | org/hr |
| | | | | | | | | | |
19 | Bongkar rabat beton | | | | M2 | pekerja | | | 0.05 | org/hr |
| | | | | | mandor | | | 0.0025 | org/hr |
| | | | | | | | | | |
20 | Bongkar bak air teraso | | | | BH | pekerja | | | 0.3 | org/hr |
| | | | | | mandor | | | 0.015 | org/hr |
terima kasih sangat membantu.
ReplyDeleteterimakasih
ReplyDeleteterimakasih
ReplyDeleteini dari SNI atau dari mana pak.?
ReplyDeleteIni bukan SNI...ni analisa tukang...
ReplyDeleteKalau harga bongkar pondasi permeter berapa ?
ReplyDeletethx
ReplyDeleteAnalisa yg me ngitelllkan diri
ReplyDeleteTks membatu pekerjaan sekali
ReplyDeleteterima kasih atas pencerahannya
ReplyDeleteSekarang ini berapa upah kerja bongkar dinding keramik +campuranx dan kramik lantai?
ReplyDelete