III | PEKERJAAN BETON : | | | | | | | | | |
| | | | | | | | | | |
1 | Beton 1:3:5 | | | | M3 | semen | | | 4.54 | zak |
| | | | | | pasir beton | | | 0.54 | m3 |
| | | | | | split | | | 0.91 | m3 |
| | | | | | tk. Batu | | | 1 | org/hr |
| | | | | | kepala tukang batu | | | 0.1 | org/hr |
| | | | | | pekerja | | | 3 | org/hr |
| | | | | | mandor | | | 0.1 | org/hr |
| | | | | | | | | | |
2 | Beton 1:2:3 | | | | M3 | semen | | | 6.8 | zak |
| | | | | | pasir beton | | | 0.54 | m3 |
| | | | | | split | | | 0.82 | m3 |
| | | | | | tk. Batu | | | 1 | hr |
| | | | | | kepala tukang batu | | | 0.1 | hr |
| | | | | | pekerja | | | 3 | hr |
| | | | | | mandor | | | 0.1 | hr |
| | | | | | | | | | |
3 | Beton K225 | | | | M3 | semen | | | 6.8 | |
| | | | | | pasir beton | | | 0.54 | m3 |
| | | | | | split | | | 0.82 | m3 |
| | | | | | tk. Batu | | | 1 | hr |
| | | | | | kepala tukang batu | | | 0.1 | hr |
| | | | | | pekerja | | | 3 | hr |
| | | | | | mandor | | | 0.1 | hr |
| | | | | | | | | | |
4 | Beton K175 (ready mix) | | | | M3 | beton ready mix K.175 | | | 1.05 | m3 |
| | | | | | sewa pompa | | | 1 | m3 |
| | | | | | tk. Batu | | | 0.4 | org/hr |
| | | | | | kepala tukang batu | | | 0.04 | org/hr |
| | | | | | pekerja | | | 1.5 | org/hr |
| | | | | | mandor | | | 0.075 | org/hr |
| | | | | | | | | | |
5 | Beton K225 (ready mix) | | | | M3 | beton ready mix K225 | | | 1.05 | m3 |
| | | | | | sewa pompa | | | 1 | m3 |
| | | | | | tk. Batu | | | 0.4 | org/hr |
| | | | | | kepala tukang batu | | | 0.04 | org/hr |
| | | | | | pekerja | | | 1.5 | org/hr |
| | | | | | mandor | | | 0.075 | org/hr |
| | | | | | | | | | |
6 | Beton K.300 (ready mix) | | | | M3 | beton ready mix K300 | | | 1.05 | m3 |
| | | | | | sewa pompa | | | 1 | m3 |
| | | | | | tk. Batu | | | 0.4 | org/hr |
| | | | | | kepala tukang batu | | | 0.04 | org/hr |
| | | | | | pekerja | | | 1.5 | org/hr |
| | | | | | mandor | | | 0.075 | org/hr |
| | | | | | | | | | |
7 | Pekerjaan besi beton 1 kg | | | | Kg | besi beton | | | 1.05 | kg |
| (U-24) | | | | | kawat beton | | | 0.01 | kg |
| | | | | | tk. Besi | | | 0.03 | org/hr |
| | | | | | kepala tukang besi beton | | | 0.015 | org/hr |
| | | | | | pekerja | | | 0.04 | org/hr |
| | | | | | | | | | |
| | | | | | | | | | |
8 | Pekerjaan besi beton 1 kg | | | | Kg | besi beton | | | 1.05 | kg |
| (U-36) | | | | | kawat beton | | | 0.01 | kg |
| | | | | | tk. Besi | | | 0.03 | org/hr |
| | | | | | kepala tukang besi beton | | | 0.015 | org/hr |
| | | | | | pekerja | | | 0.04 | org/hr |
| | | | | | | | | | |
9 | Pekerjaan Wiremesh M8 | | | | M2 | Wiremesh M8 | | | 1.01 | m2 |
| | | | | | Kawat las | | | 0.1 | kg |
| | | | | | pekerja | | | 0.1 | org/hr |
| | | | | | tukang besi | | | 0.075 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
10 | Bekesting beton kolom | | | | M2 | triplek 12 mm | | | 0.35 | lbr |
| | | | | | paku rata-rata | | | 0.4 | kg |
| | | | | | kaso meranti utk. Rangka | | | 0.012 | m3 |
| | | | | | kaso meranti utk stut | | | 0.028 | m3 |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
11 | Bekisting beton plat/ balok | | | | M2 | triplek 12 mm | | | 0.35 | lbr |
| | | | | | paku rata-rata | | | 0.4 | kg |
| | | | | | kaso meranti utk. Rangka | | | 0.012 | m3 |
| | | | | | kaso meranti utk stut | | | 0.042 | m3 |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
12 | Bekisting beton plat/ balok | | | | M2 | kaso meranti utk. Rangka | | | 0.012 | m3 |
| dgn pendukung lantai bondex | | | | | kaso meranti utk stut | | | 0.042 | m3 |
| | | | | | paku rata-rata | | | 0.25 | kg |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
13 | Pekerjaan Bondex | | | | M2 | bondex | | | 1.01 | m2 |
| | | | | | kawat las | | | 0.1 | kg |
| | | | | | pekerja | | | 0.05 | org/hr |
| | | | | | tukang las | | | 0.03 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | shear connector | | | 1 | ls |
| | | | | | | | | | |
14 | Bekesting beton sloof & | | | | M2 | triplek 12 mm | | | 0.35 | lbr |
| pondasi palt | | | | | paku rata-rata | | | 0.4 | kg |
| | | | | | kaso meranti utk. Rangka | | | 0.012 | m3 |
| | | | | | kaso meranti utk stut | | | 0.014 | m3 |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
15 | Bekesting beton listplank | | | | M2 | triplek 12 mm | | | 0.35 | lbr |
| tebal = 10 cm | | | | | paku rata-rata | | | 0.4 | kg |
| | | | | | kaso meranti utk. Rangka | | | 0.018 | m3 |
| | | | | | kaso meranti utk stut | | | 0.03 | m3 |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
16 | Bekesting dinding beton | | | | M2 | triplek 12 mm | | | 0.35 | lbr |
| tebal dinding = 12 cm | | | | | paku rata-rata | | | 0.4 | kg |
| | | | | | kaso meranti utk. Rangka | | | 0.012 | m3 |
| | | | | | kaso meranti utk stut | | | 0.028 | m3 |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
17 | Bekesting beton tangga | | | | M2 | triplek 12 mm | | | 0.35 | lbr |
| | | | | | paku rata-rata | | | 0.4 | kg |
| | | | | | kaso meranti utk. Rangka | | | 0.018 | m3 |
| | | | | | kaso meranti utk stut | | | 0.032 | m3 |
| | | | | | tk. Kayu | | | 0.5 | org/hr |
| | | | | | kepala tukang kayu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | pekerja utk bongkar | | | 0.4 | org/hr |
| | | | | | | | | | |
18 | Sewa scafolding/ bulan | | | | M2 | main frame | | | 0.6 | bh |
| (tinggi 3 m) | | | | | cross brace | | | 0.84 | bh |
| | | | | | cross brace | | | 0.71 | bh |
| | | | | | ladder frame | | | 0.53 | bh |
| | | | | | joint plate | | | 1.13 | bh |
| | | | | | jack plate | | | 1.13 | bh |
| | | | | | head jack | | | 1.13 | bh |
| | | | | | pipe support | | | 0.27 | bh |
| | | | | | | | | | |
| ongkos bongkar pasang | | | | | ongkos bongkar pasang | | | 1 | m2 |
| | | | | | | | | | |
19 | Cor rabat beton | | | | M2 | semen | | | 0.454 | zak |
| (beton 1:3:5, tebal 10 cm) | | | | | pasir beton | | | 0.054 | m3 |
| | | | | | split | | | 0.091 | m3 |
| | | | | | tukang batu | | | 0.1 | org/hr |
| | | | | | kepala tukang batu | | | 0.01 | org/hr |
| | | | | | pekerja | | | 0.3 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
20 | Cor beton 1:3:5 | | | | M2 | semen | | | 4.54 | zak |
| | | | | | pasir beton | | | 0.54 | m3 |
| | | | | | split | | | 0.91 | m3 |
| | | | | | tukang batu | | | 1 | org/hr |
| | | | | | kepala tukang batu | | | 0.1 | org/hr |
| | | | | | pekerja | | | 3 | org/hr |
| | | | | | mandor | | | 0.1 | org/hr |