IV | PEKERJAAN PASANGAN | | | | | | | | | |
| | | | | | | | | | |
1 | Aanstamping batu kali | | | | M3 | batu kali | | | 1.2 | m3 |
| | | | | | pasir pasang | | | 0.44 | m3 |
| | | | | | pekerja | | | 1.5 | org/hr |
| | | | | | mandor | | | 0.075 | org/hr |
| | | | | | | | | | |
2 | Pas. Pondasi batu kali 1:2 | | | | M3 | batu kali | | | 1.2 | m3 |
| | | | | | semen | | | 3.52 | zak |
| | | | | | pasir pasang | | | 0.38 | m3 |
| | | | | | tk. Batu | | | 0.6 | org/hr |
| | | | | | kepala tukang batu | | | 0.06 | org/hr |
| | | | | | pekerja | | | 2.25 | org/hr |
| | | | | | mandor | | | 0.017 | org/hr |
| | | | | | | | | | |
3 | Pas. Pondasi batu kali 1:4 | | | | M3 | batu kali | | | 1.2 | m3 |
| | | | | | semen | | | 1.76 | zak |
| | | | | | pasir pasang | | | 0.76 | m3 |
| | | | | | tk. Batu | | | 0.6 | org/hr |
| | | | | | kepala tukang batu | | | 0.06 | org/hr |
| | | | | | pekerja | | | 2.25 | org/hr |
| | | | | | mandor | | | 0.017 | org/hr |
| | | | | | | | | | |
4 | Pas. Pondasi batu kali 1:4 | | | | M3 | batu kali | | | 1.5 | m3 |
| memakai batu muka + siaran | | | | | semen | | | 1.76 | zak |
| | | | | | pasir pasang | | | 0.76 | m3 |
| | | | | | tk. Batu | | | 1.2 | org/hr |
| | | | | | kepala tukang batu | | | 0.12 | org/hr |
| | | | | | pekerja | | | 2.25 | org/hr |
| | | | | | mandor | | | 0.017 | org/hr |
| | | | | | | | | | |
5 | Pas. Batu tempel + siaran | | | | M3 | batu tempel | | | 1.1 | m2 |
| | | | | | semen | | | 0.12 | zak |
| | | | | | pasir pasang | | | 0.032 | m3 |
| | | | | | tk. Batu | | | 0.3 | org/hr |
| | | | | | kepala tukang batu | | | 0.05 | org/hr |
| | | | | | pekerja | | | 0.375 | org/hr |
| | | | | | mandor | | | 0.034 | org/hr |
6 | Pas. Pondasi rollag bata 1:4 | | | | M3 | batu bata merah | | | 475 | bh |
| | | | | | semen | | | 2.4 | zak |
| | | | | | pasir pasang | | | 0.416 | m3 |
| | | | | | tk. Batu | | | 1.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.15 | org/hr |
| | | | | | pekerja | | | 3 | org/hr |
| | | | | | mandor | | | 0.15 | org/hr |
| | | | | | | | | | |
7 | Pas. Pondasi roollag bata 1:4 | | | | M' | | | | 0.07 | |
| | | | | | | | | | |
8 | Pas. Dinding batu bata 1:2 | | | | M2 | batu bata merah | | | 75 | bh |
| | | | | | semen | | | 0.58 | zak |
| | | | | | pasir pasang | | | 0.047 | m3 |
| | | | | | tk. Batu | | | 0.2 | org/hr |
| | | | | | kepala tukang batu | | | 0.02 | org/hr |
| | | | | | pekerja | | | 0.5 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
9 | Pas. Dinding batu bata 1:4 | | | | M2 | batu bata merah | | | 75 | bh |
| | | | | | semen | | | 0.354 | zak |
| | | | | | pasir pasang | | | 0.057 | m3 |
| | | | | | tk. Batu | | | 0.2 | org/hr |
| | | | | | kepala tukang batu | | | 0.02 | org/hr |
| | | | | | pekerja | | | 0.5 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
10 | Pas. Dinding batu bata 1:2 | | | | M3 | batu bata merah | | | 500 | bh |
| | | | | | semen | | | 4.12 | zak |
| | | | | | pasir pasang | | | 0.333 | m3 |
| | | | | | tk. Batu | | | 1.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.15 | org/hr |
| | | | | | pekerja | | | 4.5 | org/hr |
| | | | | | mandor | | | 0.225 | org/hr |
| | | | | | | | | | |
11 | Pas. Dinding batu bata 1:4 | | | | M3 | batu bata merah | | | 500 | bh |
| | | | | | semen | | | 2.53 | zak |
| | | | | | pasir pasang | | | 0.406 | m3 |
| | | | | | tk. Batu | | | 1.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.15 | org/hr |
| | | | | | pekerja | | | 4.5 | org/hr |
| | | | | | mandor | | | 0.225 | org/hr |
| | | | | | | | | | |
12 | Pas. Rooster beton 20x20x7 | | | | M2 | rooster beton 20.20.7 cm | | | 25 | bh |
| adukan 1:2 | | | | | semen | | | 0.172 | zak |
| | | | | | pasir pasang | | | 0.017 | m3 |
| | | | | | tk. Batu | | | 0.18 | org/hr |
| | | | | | kepala tukang batu | | | 0.018 | org/hr |
| | | | | | pekerja | | | 0.54 | org/hr |
| | | | | | mandor | | | 0.027 | org/hr |
| | | | | | | | | | |
13 | Pas. Rooster bata merah | | | | M2 | rooster bata merah | | | 33 | bh |
| uk. 12x12x11.5 | | | | | semen | | | 0.2 | zak |
| adukan 1:2 | | | | | pasir pasang | | | 0.016 | m3 |
| | | | | | tk. Batu | | | 0.18 | org/hr |
| | | | | | kepala tukang batu | | | 0.018 | org/hr |
| | | | | | pekerja | | | 0.54 | org/hr |
| | | | | | mandor | | | 0.027 | org/hr |
| | | | | | | | | | |
14 | Pas. Bataco press 40x19x9 | | | | M2 | bataco press | | | 13 | bh |
| adukan 1:2 | | | | | semen | | | 0.103 | zak |
| | | | | | pasir pasang | | | 0.02 | m3 |
| | | | | | tk. Batu | | | 0.18 | org/hr |
| | | | | | kepala tukang batu | | | 0.018 | org/hr |
| | | | | | pekerja | | | 0.54 | org/hr |
| | | | | | mandor | | | 0.027 | org/hr |