VI | PEKERJAAN LANTAI : | | | | | | | | | |
| | | | | | | | | | |
1 | Pasangan lantai keramik 10x20 | | | | M2 | lantai keramik 10/20 | | | 1.05 | m2 |
| (polos) | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.2 | zak |
| | | | | | semen warna | | | 0.14 | kg |
| | | | | | tk. Batu | | | 0.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.075 | org/hr |
| | | | | | pekerja | | | 0.3 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
2 | Pasangan lantai keramik 20x20 | | | | M2 | lantai keramik 20/20 | | | 1.05 | m2 |
| (polos) | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.2 | zak |
| | | | | | semen warna | | | 0.4 | kg |
| | | | | | tk. Batu | | | 0.075 | org/hr |
| | | | | | kepala tukang batu | | | 0.2 | org/hr |
| | | | | | pekerja | | | 0.02 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
3 | Pasangan lantai keramik 20x20 KM/WC | | | | M2 | lantai keramik 20/20 KM/WC | | | 1.05 | m2 |
| (anti slip) | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.24 | zak |
| | | | | | semen warna | | | 0.1 | kg |
| | | | | | tk. Batu | | | 0.4 | org/hr |
| | | | | | kepala tukang batu | | | 0.1125 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.03 | org/hr |
| | | | | | | | | | |
4 | Pasangan lantai keramik 30x30 | | | | M2 | lantai keramik 30/30 | | | 1.05 | m2 |
| (polos) | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.1 | zak |
| | | | | | semen warna | | | 0.07 | kg |
| | | | | | tk. Batu | | | 0.4 | org/hr |
| | | | | | kepala tukang batu | | | 0.075 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.02 | org/hr |
| | | | | | | | | | |
5 | Pasang granito tile Essenza 40x40 | | | | M2 | lantai essenza 40x40 | | | 1.05 | m2 |
| (ivory unpolish) | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.2 | zak |
| | | | | | grouting lantai | | | 1 | m2 |
| | | | | | tk. Batu | | | 0.6 | org/hr |
| | | | | | kepala tukang batu | | | 0.075 | org/hr |
| | | | | | pekerja | | | 0.25 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
6 | Pas. Lantai marmer 40x60 | | | | M2 | lantai marmer 40x60 | | | 1.05 | m2 |
| tebal 2 cm | | | | | pasir pasang | | | 0.04 | m3 |
| | | | | | semen | | | 0.4 | zak |
| | | | | | grouting lantai | | | 1 | m2 |
| | | | | | tk. Batu | | | 1.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.075 | org/hr |
| | | | | | pekerja | | | 0.5 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
7 | Pasang lantai granit tebal 2 cm | | | | M2 | granit tebal 2 cm | | | 1.05 | m2 |
| (motif satndard) | | | | | pasir pasang | | | 0.04 | m3 |
| | | | | | semen | | | 0.4 | zak |
| | | | | | grouting lantai | | | 1 | m2 |
| | | | | | tk. Batu | | | 1.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.075 | org/hr |
| | | | | | pekerja | | | 0.5 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
8 | Dinding porselin 11x11 | | | | M2 | dinding porselin 11x11 | | | 1.05 | m2 |
| | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.2 | zak |
| | | | | | semen putih | | | 0.2 | kg |
| | | | | | tk. Batu | | | 0.75 | org/hr |
| | | | | | kepala tukang batu | | | 0.1 | org/hr |
| | | | | | pekerja | | | 0.5 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
9 | Dinding keramik 20x25 | | | | M2 | keramik dinding 20x25 | | | 1.05 | m2 |
| (polos) | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.2 | zak |
| | | | | | semen putih | | | 0.09 | kg |
| | | | | | tk. Batu | | | 0.6 | org/hr |
| | | | | | kepala tukang batu | | | 0.075 | org/hr |
| | | | | | pekerja | | | 0.3 | org/hr |
| | | | | | mandor | | | 0.025 | org/hr |
| | | | | | | | | | |
10 | Dinding granit ukuran besar | | | | M2 | granit DN | | | 1.05 | m2 |
| | | | | | pasir pasang | | | 0.03 | m3 |
| | | | | | semen | | | 0.3 | zak |
| | | | | | Campuran kedap air | | | 1 | kg |
| | | | | | tk. Batu | | | 1.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.1 | org/hr |
| | | | | | pekerja | | | 0.5 | org/hr |
| | | | | | mandor | | | 0.05 | org/hr |
| | | | | | | | | | |
11 | Plint keramik 10x20 | | | | M' | plint keramik 10x20 | | | 1.01 | m' |
| | | | | | semen | | | 0.02 | zak |
| | | | | | pasir pasang | | | 0.002 | m3 |
| | | | | | tk. Batu | | | 0.1 | org/hr |
| | | | | | kepala tukang batu | | | 0.01 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
12 | Plint keramik 10x30 | | | | M' | plint keramik 10x30 | | | 1.01 | m' |
| | | | | | semen | | | 0.02 | zak |
| | | | | | pasir pasang | | | 0.002 | m3 |
| | | | | | tk. Batu | | | 0.1 | org/hr |
| | | | | | kepala tukang batu | | | 0.01 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
13 | Step Noising Roman 10x20 | | | | M' | Step Noising Roman 10x20 | | | 5 | bh |
| | | | | | semen | | | 0.02 | zak |
| | | | | | pasir pasang | | | 0.002 | m3 |
| | | | | | tk. Batu | | | 0.1 | org/hr |
| | | | | | kepala tukang batu | | | 0.01 | org/hr |
| | | | | | pekerja | | | 0.2 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
14 | Poles marmer/ teraso | | | | M2 | bubuk poles lantai | | | 0.1 | kg |
| | | | | | semen putih | | | 1 | kg |
| | | | | | semir kilap lantai | | | 0.035 | kg |
| | | | | | mesin poles | | | 0.075 | unit |
| | | | | | tukang poles | | | 0.5 | org/hr |
| | | | | | kepala tukang batu | | | 0.125 | org/hr |
| | | | | | pekerja | | | 0.25 | org/hr |
| | | | | | mandor | | | 0.01 | org/hr |
| | | | | | | | | | |
15 | Pasang karpet | | | | M2 | karpet executive | | | 1 | m2 |
| | | | | | foam (underlayer) | | | 1 | m2 |
| | | | | | alat bantu (lem, paku, list dll) | | | 1 | m2 |
| | | | | | ongkos pasang | | | 1 | m2 |