CONTOH ANALISA PEKERJAAN LANTAI

VIPEKERJAAN LANTAI :
1Pasangan lantai keramik 10x20M2lantai keramik 10/201.05m2
(polos)pasir pasang0.03m3
semen0.2zak
semen warna0.14kg
tk. Batu0.5org/hr
kepala tukang batu 0.075org/hr
pekerja0.3org/hr
mandor0.025org/hr
2Pasangan lantai keramik 20x20M2lantai keramik 20/201.05m2
(polos)pasir pasang0.03m3
semen0.2zak
semen warna0.4kg
tk. Batu0.075org/hr
kepala tukang batu 0.2org/hr
pekerja0.02org/hr
mandor0.025org/hr
3Pasangan lantai keramik 20x20 KM/WCM2lantai keramik 20/20 KM/WC1.05m2
(anti slip)pasir pasang0.03m3
semen0.24zak
semen warna0.1kg
tk. Batu0.4org/hr
kepala tukang batu 0.1125org/hr
pekerja0.2org/hr
mandor0.03org/hr
4Pasangan lantai keramik 30x30M2lantai keramik 30/301.05m2
(polos)pasir pasang0.03m3
semen0.1zak
semen warna0.07kg
tk. Batu0.4org/hr
kepala tukang batu 0.075org/hr
pekerja0.2org/hr
mandor0.02org/hr
5Pasang granito tile Essenza 40x40M2lantai essenza 40x401.05m2
(ivory unpolish)pasir pasang0.03m3
semen0.2zak
grouting lantai1m2
tk. Batu0.6org/hr
kepala tukang batu 0.075org/hr
pekerja0.25org/hr
mandor0.025org/hr
6Pas. Lantai marmer 40x60M2lantai marmer 40x601.05m2
tebal 2 cm pasir pasang0.04m3
semen0.4zak
grouting lantai1m2
tk. Batu1.5org/hr
kepala tukang batu 0.075org/hr
pekerja0.5org/hr
mandor0.025org/hr
7Pasang lantai granit tebal 2 cm M2granit tebal 2 cm 1.05m2
(motif satndard)pasir pasang0.04m3
semen0.4zak
grouting lantai1m2
tk. Batu1.5org/hr
kepala tukang batu 0.075org/hr
pekerja0.5org/hr
mandor0.025org/hr
8Dinding porselin 11x11M2dinding porselin 11x111.05m2
pasir pasang0.03m3
semen0.2zak
semen putih0.2kg
tk. Batu0.75org/hr
kepala tukang batu 0.1org/hr
pekerja0.5org/hr
mandor0.025org/hr
9Dinding keramik 20x25M2keramik dinding 20x251.05m2
(polos)pasir pasang0.03m3
semen0.2zak
semen putih0.09kg
tk. Batu0.6org/hr
kepala tukang batu 0.075org/hr
pekerja0.3org/hr
mandor0.025org/hr
10Dinding granit ukuran besarM2granit DN1.05m2
pasir pasang0.03m3
semen0.3zak
Campuran kedap air1kg
tk. Batu1.5org/hr
kepala tukang batu 0.1org/hr
pekerja0.5org/hr
mandor0.05org/hr
11Plint keramik 10x20M'plint keramik 10x201.01m'
semen0.02zak
pasir pasang0.002m3
tk. Batu0.1org/hr
kepala tukang batu 0.01org/hr
pekerja0.2org/hr
mandor0.01org/hr
12Plint keramik 10x30M'plint keramik 10x301.01m'
semen0.02zak
pasir pasang0.002m3
tk. Batu0.1org/hr
kepala tukang batu 0.01org/hr
pekerja0.2org/hr
mandor0.01org/hr
13Step Noising Roman 10x20M'Step Noising Roman 10x205bh
semen0.02zak
pasir pasang0.002m3
tk. Batu0.1org/hr
kepala tukang batu 0.01org/hr
pekerja0.2org/hr
mandor0.01org/hr
14Poles marmer/ terasoM2bubuk poles lantai0.1kg
semen putih1kg
semir kilap lantai0.035kg
mesin poles0.075unit
tukang poles0.5org/hr
kepala tukang batu 0.125org/hr
pekerja0.25org/hr
mandor0.01org/hr
15Pasang karpetM2karpet executive1m2
foam (underlayer)1m2
alat bantu (lem, paku, list dll)1m2
ongkos pasang1m2